4th Street from Minnesota Avenue to Main Avenue
Project Update: 6/26/2020
- Project is complete!
2020 Project Milestones
- Road closed
- Surface removals and grading
- Watermain, sanitary and storm sewer installation
- Curb and gutter and concrete surfacing
- Landscaping
- Open to traffic
Commuter Route Information:
- Open to traffic!
Project Overview
Completion Date:
July 2020
Contract Amount:
$1,800,000
Project Summary:
The project consists of complete reconstruction of 4th St from Minnesota Avenue to Main Avenue. Work will include replacement of watermain, sanitary and storm sewer, concrete pavement, sidewalk, colored sidewalk, colored, pedestrian lighting and landscaping.
Contact Infomation
City of Sioux Falls
Dena Knutson
dknutson@siouxfalls.org
605 367-8360
Consultant Name:
HDR
Paul Sanow
605 977-7756
Paul.Sanow@hdrinc.com
Contractor Name:
TBD